§ 10-6. Permit review.  


Latest version.
  • (a)

    Upon submission of a complete application for an event permit under Section 10-4, the County administrator or designee shall have 30 days to either approve or reject the permit application. A permit application shall be rejected unless the applicant makes an affidavit swearing that all of the itemized requirements of Section 10-4 will be met.

    (b)

    Denial of a permit application shall constitute final agency action such that the denial can be appealed to the circuit court.

(Ord. No. 2003-064, § 6, 9-23-2003)